The checklist
- Collect loads. Ask caterer, AV, lighting, AC and venue for kW and phase per item.
- Size the generator. Total kW divided by 0.8, plus 20 to 25 percent. See sizing guide.
- Split critical loads. Sound and lighting on one supply, catering on another, so a fryer trip does not kill the stage.
- Plan distribution. One board per area: stage, kitchen, tent, toilets.
- Plan cable runs. Measure from generator to each board. Long runs need thicker cable.
- Place the generator. Downwind, away from guests, on level ground, with access for refuelling.
- Backup. For weddings and launches, a second unit or automatic changeover.
- Fuel. Setup day, rehearsal and event hours. See fuel chart.
- Technician. A standby technician on the night for anything over about 60 kVA.
- Permits. Check venue and community rules on generators and noise.